|
|
|
|
|
Sales Tax Review |
|
December 2007 |
|
Tax Digest |
-
Can the assessing authority revise the interest levied
under section 36(3)(b) read with section 9(2) of the Central Sales Tax Act
after the lapse of 2 years or is it an original action for which there is no
statutory limit as held by the appellate authority?
Ans: No. It is not an original order and statutory
provisions of section 62 apply.
In this case the assessment under the Bombay Sales Tax Act
for the period 1993-94 resulted in a refund of Rs. 6,35,251/-. However, the
assessing authority imposed interest under section 36(3)(a) at Rs. 36,730/-
for the delay in payments and after adjusting the said interest the net refund
was sanctioned at Rs. 5,98,521/-. For the same period the assessment under the
Central Act resulted in a demand of Rs. 8,71,642/- After taking into
consideration the gross refund of Rs. 6,35,251/- the assessing authority
levied interest under section 36(3)(b) read with section 9(2) at Rs.
2,17,480/. The assessee accepted the assessment orders and paid the balance
amount of Rs. 4,90,601/- under the Central Act.
After a period of about 7 years, the assessing authority
felt that there is a short levy of interest under section 36(3)(b) read with
section 9(2) to the extent of considering the gross refund for the purpose of
levying interest instead of net refund under the Bombay Sales Tax Act. He
worked out the interest on the differential dues at Rs. 33,791/- under section
36(3)(b) read with section 9(2) of the Central Act. The contention of the
appellant that the action is under section 62 of the Bombay Sales Tax Act,
1959 and barred by limitation was not accepted. In appeal before the Deputy
Commissioner the appellant again pleaded that the action is barred by
limitation. However, the learned Deputy Commissioner held that the action is
an original action for which there is no statutory limit.
The Tribunal after considering the rival submissions held
while passing the assessment order the assessing authority had considered the
taxes paid and payable under both the Acts and arrived at the unpaid tax
liability for the purpose of calculation of interest under section 36(3)(b).
Thus the original action to levy the interest under section 36(3)(b) was
already taken by the assessing authority through his assessment order.
According to the Tribunal if after taking this action the assessing authority
is of the opinion that there is a short levy of interest due to the
differential tax dues having been adjusted towards the gross refund instead of
the net refund, it is an error in calculation and can be corrected only by
following the remedies provided under the Act. The correction has to be made
within the particular statutory time limit. The Tribunal did not accept the
contention that the impugned action to levy additional amount of interest is
an original action under section 9(2) read with section 36(3)(b) of the Bombay
Sales Tax Act 1959. The interest under section 36(3)(b) is leviable with
reference to the differential tax dues as per the assessment order for a given
period and therefore the original action to levy such interest can be taken
only once. Once such original action is taken, any subsequent variation in the
interest has to be made through the actions as provided in sections 62, 35,
55, 57 etc. As the action was taken after a lapse of 7 years, it was clearly
barred by limitation. On merits also the Tribunal held the action of taking
net refund to determine the CST tax dues for the purpose of levy of interest
is legally unsustainable in the light of the Tribunal’s judgment in the case
of Royal Agencies (S.A. 1454 of 2002 dated 20-12-2003).
(Skol Breweries Limited vs. The State of Maharashtra –
Second Appeal No. 1323 of 2006 dated 9th February, 2007. The judgment is
delivered at the Third Bench of the Tribunal by the Hon’ble Member G.G.
Kochrekar. The appellant was represented by B. D. Advani, Advocate.)
-
Whether the appellant is entitled to set off under Rule
41D(2)(iii) of the Bombay Sales Tax Act, 1959 in the context of the goods
manufactured and transferred to branches which are used in the execution of
Works Contract in other States.
Ans. Yes.
The appellant is a manufacturer of paint booths, paint
systems, spares, components and accessories required for the said machineries.
The appellant had branch transferred the manufactured goods to its Gurgaon
Branch. The said branch is registered under the Central Act and had issued
Form 31C duly filled in and signed by the Manager. The appellant had claimed
set off under Rule 41D(2) (iii) in respect of the said branch transfer. The
Assessing Officer disallowed the set off and in appeal the action of the
Officer was upheld. Before the Tribunal the appellant pointed out the relevant
portion of the Rule and the term “Export”in the said rule and submitted that
it had fulfilled all the conditions. It was also argued that if at all the
term “sale” is to be interpreted, it has to be as per the provisions of the
law applicable in the State where the contract is executed; i.e., Haryana and
Works Contracts have been treated as sales under the Haryana Act. Suffice it
to say, the appellant argued that the definition of the term “sale” as per the
Bombay Act speaks only in respect of sales within Maharashtra and has no
bearing for sales effected outside the State of Maharashtra. In support of his
plea, the appellant has also referred o the decision of the Tribunal in Shirke
Construction Equipments Pvt. Ltd (S.A.1557 of 1993 dated 31-10-1996) and B.G.
Shirke Construction Technology Pvt. Ltd. (S.A. No.1410 of 2001 dated
15-3-2003). In the said cases the Tribunal has also referred to Circular No.13
of 1987 issued by the Commissioner. The Tribunal therefore held that the
appellant is eligible for set off under Rule 41D(2)(iii) in the context of the
use of the manufactured goods in the execution of works contracts in other
States subject to fulfilling other conditions.
(M/s Thermax Surface Paints Limited vs. The State of
Maharashtra (Second Appeal No.62 of 2005 dated 20th April 2007. The judgment
is delivered at the First Bench by the Hon’ble President Mr. G. D. Parekh. The
appellant was represented by Mr. A.B.Ghanekar, Sales Tax Practitioner.)
-
Whether the contract for erection/construction of 400 KV
LILO involving use of building material would be a civil construction contract
for the purpose of sub-section (1) of section 6A of the Works Contract Act?
Ans: Yes.
The facts in brief are:– The Maharashtra State Electricity
Board awarded a contract in favour of the appellant for construction of 400 KV
LILO to Aurangabad on 400 KV Bhusaval-Bhabhaleshwar S/C line. The scope of the
work involves excavation, stub foundation, back filling, tower erection,
stringing of earth wire, conductor protection etc. All the material such as
towers with accessories, earthing set, insulators with hand wares, conductors,
and earth wire will be supplied by MSEB. However, cement, steel, metal, sand,
stone water back filling material coke etc. required for foundation and tower
footing protection and earthing will be arranged by the appellant. The
assessing authority as well as the first Appellate Authority treated the
contract as a non construction contract and levied tax under the Works
Contract Act by following Government Notification dated 8-3-2000 specifying
the contracts mentioned therein to be only construction contracts for the
purpose of sub-section (1) of section 6A of the Works Contract Act. The
periods involved in these appeals are 1999-00 and 2000-01.
The appellant submitted before the Tribunal that an
explanation is added to sub-section (1) of section 6A by Maharashtra Act No.1
of 2000 dated 1-1-2000, providing that for the purpose of the sub-section the
expression construction contract shall mean such contract as may be notified
by the State Government from time to time. In view of the said explanation the
Government has issued Notification on 8-3-2000 specifying the contracts to be
construction contracts. According to the appellant prior to 8-3-2000 the
expression “construction contract” was not defined in the WCT Act or Rule made
thereunder. In the absence of definition of construction contract it has to be
interpreted with reference to the dictionary meaning. According to the
appellant up to 8-3-2000 all contracts which could be legitimately held as
construction contracts were covered by the scope of section 6A attracting the
composition rate of 1% in respect of the contracts awarded and executed prior
to 1-5-1998 and 2% for construction contracts after 1-5-1998 as applicable. So
far as the period after 8-3-2000, according to the appellant the contracts
notified are only illustrative and not exhaustive and therefore the type of
contract which he undertakes would also be covered in construction contracts.
The object of issuing the Notification is to give benefit of lower rate of
composition to the civil work.
The Tribunal observed that prior to the Notification dated
8-3-2000 the expression “construction contract” was not defined. The
Notification dated 8-3-2000 is not issued retrospectively for the reason that
the explanation is added to sub-section (1) of section 6A by Amendment Act
dated 1-1-2000 and thereby the Government is empowered to Notify the contract
as construction contract. According to the Tribunal the Notification dated
8-3-2000 cannot be taken help of to determine the nature of the contract as
construction contract or otherwise prior to 8-3-2000. The Tribunal also
discussed the work involved in the erection of Tower. It also examined the
Schedule of the item wise rate appended to the Work Order in Parts A & B
issued by MSEB. After considering the entire work the Tribunal came to the
conclusion that the work executed by the appellant involves major civil work
compared to the cost of erection of towers and related work and the contract
is therefore predominantly a civil contract liable to composition rate of 2%
prior to 8-3-2000.
The Tribunal further held that as far as the period after
8-3-2000, the position as to the construction contract is unambiguous. The
State Government is empowered to Notify the contracts as Construction
contracts in the Official Gazette from time to time. It has notified the
contracts mentioned in the Notification dated 8-3-2000 to be construction
contracts. The contract of erection of transmission tower executed by the
appellant is not covered by the said Notification.
(Electrical Manufacturing Co. Ltd. vs. The State of
Maharashtra - Second Appeal Nos. 286 and 287 of 2006 dated 5th May 2007. The
judgment is delivered at the Fourth Bench by the Hon’ble Member Mr. D.H. Sali.
The appellant was represented by Mr. A.B.Ghanekar, Sales Tax Practitioner.)
|
|
|